Dear Lacey MUA,

This is a request for public records made under OPRA and the common law right of access. I am not required to fill out an official form. Please acknowledge receipt of this message.
Records requested:

For the purpose of this OPRA request, I am referring to the South Winds Water Main project (the "project") as approved by the Authority in resolution 2018-62 and the Interlocal Services Agreement.

Please provide the following documents regarding the project:

1 - Copy of engineer's study substantiating the need for an 8" water main for the purpose of fire protection at 362 E. Lacey Road.

2 - Copies of all plans for the project submitted to the Authority.

3 - Copies of all letters received from the New Jersey State Fire Marshal's Office regarding the need for an 8" water line.

Yours faithfully,

Gavin Rozzi

Dear Lacey MUA,

I am adding an addendum to this OPRA request. Please add this additional item:

4 - Parts list for the project showing parts needed for the water main.

Yours faithfully,

Gavin Rozzi

edward woolf, Lacey MUA

Mr. Rozzi,
OPRA request received.
 Regards,
Edward A. Woolf
Executive Director
Lacey Municipal Utilities Authority
124 South Main St.
P.O. Box 205
Forked River, NJ 08731

--------------------------------------------------------------------------

From: Gavin Rozzi <[OPRA #3692 email]>
To: OPRA requests at Lacey MUA <[Lacey MUA request email]>
Sent: Tuesday, January 22, 2019 7:03 PM
Subject: OPRA request - South Winds water line documents
Dear Lacey MUA,
This is a request for public records made under OPRA and the common law
right of access. I am not required to fill out an official form. Please
acknowledge receipt of this message.
  Records requested:
For the purpose of this OPRA request, I am referring to the South Winds
Water Main project (the "project") as approved by the Authority in
resolution 2018-62 and the Interlocal Services Agreement.
Please provide the following documents regarding the project:
1 - Copy of engineer's study substantiating the need for an 8" water main
for the purpose of fire protection at 362 E. Lacey Road.
2 - Copies of all plans for the project submitted to the Authority.
3 - Copies of all letters received from the New Jersey State Fire
Marshall's Office regarding the need for an 8" water line.
Yours faithfully,
Gavin Rozzi
-------------------------------------------------------------------
Please use deliver records electronically via email to the below UNIQUE
address for all replies to this request:
opra+[1][email address]
Is [2][Lacey MUA request email] the wrong address for OPRA requests to Lacey
MUA? If so, please contact us using this form:
[3]https://opramachine.com/change_request/n...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[4]https://opramachine.com/help/officers
View this OPRA request & responses online:
[5]https://opramachine.com/request/south_wi...
Please note that in some cases publication of requests and responses will
be delayed.
If you find this service useful as an OPRA custodian, please ask your web
manager to link to us from your organisation's website.
-------------------------------------------------------------------

References

Visible links
1. mailto:[email address]
2. mailto:[Lacey MUA request email]
3. https://opramachine.com/change_request/n...
4. https://opramachine.com/help/officers
5. https://opramachine.com/request/south_wi...

edward woolf, Lacey MUA

Mr. Rozzi,
OPRA request received
Regards, 
Edward A. Woolf
Executive Director
Lacey Municipal Utilities Authority
124 South Main St.
P.O. Box 205
Forked River, NJ 08731

--------------------------------------------------------------------------

From: Gavin Rozzi <[OPRA #3692 email]>
To: OPRA requests at Lacey MUA <[Lacey MUA request email]>
Sent: Tuesday, January 22, 2019 7:54 PM
Subject: Re: OPRA request - South Winds water line documents
Dear Lacey MUA,
I am adding an addendum to this OPRA request. Please add this additional
item:
4 - Parts list for the project showing parts needed for the water main.
Yours faithfully,
Gavin Rozzi
-------------------------------------------------------------------
Please use this UNIQUE email address for all replies to this request and
no other:
opra+[1][email address]
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[2]https://opramachine.com/help/officers
View this OPRA request & responses online:
[3]https://opramachine.com/request/south_wi...
Please note that in some cases publication of requests and responses will
be delayed.
If you find this service useful as an OPRA custodian, please ask your web
manager to link to us from your organisation's website.
-------------------------------------------------------------------

References

Visible links
1. mailto:[email address]
2. https://opramachine.com/help/officers
3. https://opramachine.com/request/south_wi...

edward woolf, Lacey MUA

Mr. Rozzi
Please be advised that no such documents exist at the Lacey MUA for OPRA
requests 1, 2 and 3. 
Regards,
Edward A. Woolf
Executive Director
Lacey Municipal Utilities Authority
124 South Main St.
P.O. Box 205
Forked River, NJ 08731

--------------------------------------------------------------------------

From: Gavin Rozzi <[OPRA #3692 email]>
To: OPRA requests at Lacey MUA <[Lacey MUA request email]>
Sent: Tuesday, January 22, 2019 7:03 PM
Subject: OPRA request - South Winds water line documents
Dear Lacey MUA,
This is a request for public records made under OPRA and the common law
right of access. I am not required to fill out an official form. Please
acknowledge receipt of this message.
  Records requested:
For the purpose of this OPRA request, I am referring to the South Winds
Water Main project (the "project") as approved by the Authority in
resolution 2018-62 and the Interlocal Services Agreement.
Please provide the following documents regarding the project:
1 - Copy of engineer's study substantiating the need for an 8" water main
for the purpose of fire protection at 362 E. Lacey Road.
2 - Copies of all plans for the project submitted to the Authority.
3 - Copies of all letters received from the New Jersey State Fire
Marshall's Office regarding the need for an 8" water line.
Yours faithfully,
Gavin Rozzi
-------------------------------------------------------------------
Please use deliver records electronically via email to the below UNIQUE
address for all replies to this request:
opra+[1][email address]
Is [2][Lacey MUA request email] the wrong address for OPRA requests to Lacey
MUA? If so, please contact us using this form:
[3]https://opramachine.com/change_request/n...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[4]https://opramachine.com/help/officers
View this OPRA request & responses online:
[5]https://opramachine.com/request/south_wi...
Please note that in some cases publication of requests and responses will
be delayed.
If you find this service useful as an OPRA custodian, please ask your web
manager to link to us from your organisation's website.
-------------------------------------------------------------------

References

Visible links
1. mailto:[email address]
2. mailto:[Lacey MUA request email]
3. https://opramachine.com/change_request/n...
4. https://opramachine.com/help/officers
5. https://opramachine.com/request/south_wi...

edward woolf, Lacey MUA

1 Attachment

Mr. Rozzi,
Please find the document requested in your OPRA request #4.
Regards, 
Edward A. Woolf
Executive Director
Lacey Municipal Utilities Authority
124 South Main St.
P.O. Box 205
Forked River, NJ 08731

--------------------------------------------------------------------------

From: Gavin Rozzi <[OPRA #3692 email]>
To: OPRA requests at Lacey MUA <[Lacey MUA request email]>
Sent: Tuesday, January 22, 2019 7:54 PM
Subject: Re: OPRA request - South Winds water line documents
Dear Lacey MUA,
I am adding an addendum to this OPRA request. Please add this additional
item:
4 - Parts list for the project showing parts needed for the water main.
Yours faithfully,
Gavin Rozzi
-------------------------------------------------------------------
Please use this UNIQUE email address for all replies to this request and
no other:
opra+[1][email address]
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[2]https://opramachine.com/help/officers
View this OPRA request & responses online:
[3]https://opramachine.com/request/south_wi...
Please note that in some cases publication of requests and responses will
be delayed.
If you find this service useful as an OPRA custodian, please ask your web
manager to link to us from your organisation's website.
-------------------------------------------------------------------

References

Visible links
1. mailto:[email address]
2. https://opramachine.com/help/officers
3. https://opramachine.com/request/south_wi...